Quote:
Originally Posted by Centex
For consistency I'll adopt the Canadian date format convention used by ETI
2020-09-09 Deposit Submitted via online form
2020-09-09 "Welcome" email received from ETI with Order Ref Number and "important milestones" listed: - Start of Configuration Stage: 2021-04-19 (4 months prior to completion).
- Confirmation Date/Purchase Agreement: 2021-05-18 (3 months prior to completion). Build sheet 'locked' and deposit non-refundable as of this action.
- Production Complete: 2021-08-18. Remaining balance due becomes payable at this time.
- Free storage ends: 2021-09-17 (1 month after completion).
All as per the process timeline description by Karl in the recent livestream, no surprises.
Free Storage is moot for me, I'm planning on delivery / pickup in Sumas ASAP upon availability, with the long-anticipated 'shakedown trip' returning to Texas
|
I ordered a couple of weeks earlier than you and my scheduled delivery date is Feb 2020:
Deposit date:
2020-08-25
Configuration Stage:
2020-10-26 (4 months prior to completion).
Confirmation Date/Sign off:
2020-11-26 (3 months prior to completion).
Arrange for Delivery (optional):
2021-01-26 (1 month prior to completion).
Production Complete:
2021-02-26
Free storage ends: 2021-03-26 (1 month after completion).
I called Escape before ordering and was told the expected delivery date was May 2020, when I put down the deposit and emails says it's Feb 2020. I emailed Escape and was confirmed the Feb 2020 date. This is surprising, hope it comes through in Feb.